Bathroom projects vary depending on the complexity of the installation.  Day one is always spent removing the old bathroom suite and tiles etc.  It is often the case that plasterboarded walls are damaged by the tiles and need to be removed too.  There are usually a few days of prep work such as installaing pipework, electrics and decoration.  Tiling starts and can take up to 4 days for a fully tiled room including grouting.  The new items can then be fitted.

This is a fairly standard scenario and usully takes 9-10 working days.  We don’t take breaks away from the job other than weekends so the room is finished as soon as we can make it happen.